100 MMSCFD GAS PROCESSING & WATER TREATMENT PLANT


NORTHEASTERN BC

About the Project


Under a lump sum turnkey contract, EPFC designed, fabricated and constructed a 100 MMSCFD sour gas processing plant for a major international client. The plant also processes over 20,000 bpd of hydrocarbon liquids, between LPG and C5+ stabilized condensate. EPFC was the prime contractor at the site until the plant was fully commissioned. Start up and performance validation were completed by EPFC as part of turnover to the client. In addition to the gas plant, a 5000 m3/d produced water treatment facility was included at the site. The water treatment facility recycles produced water for use as frac water in the client’s completions operations.

Major Equipment: Inlet separation, inlet compression, amine sweetening unit, refrigeration package, de-ethanizer, condensate stabilization, sales compression, LPG storage bullets, C5+ storage tanks, produced water treatment

Utilities: Instrument air, turbine-driven power generation, fuel gas, heat medium, waste heat recovery, flare system, acid gas incineration

EPFC Scope: Engineering, Procurement, Fabrication, Construction